About Lariat Trails Elementary School
In fall 2026, Liberty Hill ISD opened its largest elementary school yet, giving the district a secure, adaptable campus built to accommodate 1,000 students. Lariat Trails Elementary is a new two-story 112,992-square-foot campus in the Lariat community designed to support the district’s growing student population. Inside are 62 classrooms — four pre-K spaces plus eight for each grade K through 5 — along with dedicated rooms for art, science, makerspace projects and life skills, two music classrooms, a library, cafetorium, gym, admin offices, an outdoor playground area and plenty of flexible space for students to collaborate. The art and science rooms and media center all open onto a central courtyard, so learning doesn't have to stop at the classroom.
Fitting a campus this size onto the site came with its own challenges. The 12.65-acre lot came with major elevation changes, so instead of sitting on one flat pad, the building is built on a slope across multiple floors and ground levels, showing just how much the terrain would ultimately shape the construction of this project.
Project Quick Facts:
- Location: Liberty Hill, TX
- Client: Leander Independent School District
- Architect: VLK Architects
- Industry: K-12 Education
- Square Footage: 112,992 SF of new construction
- Delivery Date: May 2026
CHALLENGE: Managing a Sloped Site and Utility Delays
The school had to fit on just 12.65 acres of sloped, uneven ground, which is a tight footprint for a building this large. Rather than sitting on one flat pad, the campus needed to spread across the terrain at multiple floor and ground elevations, which meant the design team faced a far more complicated foundation than a typical elementary school, plus retaining walls and deep excavation in the parking areas. That same compact site made it hard to find room for tilt-wall panel casting, crane access and the sequencing of earthwork, foundations and building systems, all of which were competing for space at once.
Outside the fence line, a different problem emerged: securing a water connection through Georgetown's utility authorities took more than 12 months of easements, paperwork and approvals. Long lead times for the main electrical switchgear also created challenges.
SOLUTION: Building a Split-Level Foundation and Day-One Utility Coordination
To handle the terrain, the team designed a split-level foundation with two different interior slab elevations, excavated roughly 12 feet into the existing grade for the parking area, and built mechanically stabilized earth retaining walls, paired with waterproofing and French drains to manage groundwater. Tilt-wall construction was carefully mapped out in advance — where panels could be cast, how cranes would reach them and what order they needed to go up — so the limited space didn't stall the project schedule. A detailed master schedule, backed by weekly check-ins with all partners, kept every subcontractor aware of what needed to happen next and in what order.
For the water connection, the team treated it as its own dedicated workstream rather than a side issue by tracking every outstanding document, staying in constant contact with the district and campus, civil engineer and utility representatives and keeping other work moving in the meantime so the delay didn't stall the whole project. To meet electrical power needs, the team ordered the switchgear in advance and coordinated closely with the electrical company to align their work with the project schedule.
The team also looked for smart ways to trim cost without cutting quality such as swapping a specified rainscreen support system for standard metal furring, removing unnecessary rooftop equipment screens and simplifying an elevated outdoor slab assembly.
RESULT: Power Delivered Ahead of Schedule with over $2M Back to the District
Lariat Trails Elementary opened on schedule in fall 2026. Permanent power came online in October 2025, about eight months ahead of completion, giving interior trades a stable environment to finish their work without delay. The water utility issue, despite dragging on for over a year, never derailed the overall schedule. And the value engineering effort returned over $2M to Liberty Hill ISD while also reducing long-term material and maintenance demands. What could have been a difficult, uneven site became a fully functioning school, on time, for this growing school district.