Del Valle ISD High School #2 (Bid Package 2)

American Constructors is the the Construction Manager-at-Risk for Del Valle ISD High School #2. Project is a $240M construction of a new two-story high school. Unique features include: Auditorium, Perimeter tilt walls, Elevated hollow core structural concrete at kitchen, Geothermal loop wells, Stand-alone field house building, Athletic field events, football, baseball, and softball fields.

Bid Package 2 includes All Scopes of work, EXCEPT, Earthwork, Erosion controls and filtration pond internals, Pavement & Retaining wall concrete, Pavement Markings and Utilities.

Project Address: TEMPORARY Address: 8200 Taylor Lane, Manor, TX 78653

Project Size: Main building: 420,500 sf; Field House: 30,000 sf

  • Foundations - January 2024
  • Structure - March 2024
  • Framing & MEP Above Ground - May 2024
  • Completion - June 1, 2026

Bids are due Wednesday, 9/13/23, by 2:00 pm (CDT). Please provide your proposal to us as early in the day as possible. Bids may be emailed to estimating@americanconstructors.com, mailed/delivered to American Constructors at 11900 West Parmer Lane, Suite 200, Cedar Park, TX 78613, or submitted via fax to (512) 328-2520.

Drawings and Specifications can be downloaded from out ftp site at https://acitexas.smartfile.com

Username: actexas-951
Password:  actexas-951

Build Your Own Brochure

Download a customized brochure in just three steps.

Market Sectors

Services

Step 2

Complete this form to let us know where to send your brochure.

You're Done!

Click the button below to download your copy now or check your inbox to review the brochure at your leisure.