About Riverside Middle School

To create a broader and more specialized middle school program, Bastrop Intermediate School was converted into the new Riverside Middle School. This transformation expanded the existing intermediate school and modernized the campus to be built to serve approximately 858 students in grades 6 through 8. The upgraded campus features renovated classrooms, science laboratories and preparation areas, technology and Fine Arts spaces. There are also a variety of athletic facility improvements such as a new gym, track, weight rooms, locker rooms and tennis courts.

Project Quick Facts:

  • Location: Bastrop, TX
  • Client: Bastrop Independent School District
  • Architect: VLK Architects 
  • Industry: K-12 Education
  • Square Footage: 122,181 SF (53,584 SF of new construction, 68,597 SF of renovation)
  • Delivery Date: April 2026

CHALLENGE: Scheduling Around an Active Campus and Connecting an Old and New Roof

The conversion of Bastrop Intermediate School into Riverside Middle School was completed around an active campus, adding complexity to nearly every phase of construction. The scope included demolition, renovation, new additions, upgraded academic spaces and major utility modifications — all while maintaining safe walking pathways to and from the existing school, securely separating construction zones and coordinating shifting access conditions without disrupting school operations.

One of the earliest challenges was the location of the campus's primary electrical service, which conflicted with the location of  the new additions. To avoid delaying the work, the project team developed and executed a temporary routing plan that kept the existing school in session while clearing the construction area. The completed changeover left the campus with consolidated, expanded electrical infrastructure while preserving service to the original building.

Another unique challenge involved tying the newly constructed roof into the existing roof. Structural reinforcement inside the occupied building was required before the roof tie-ins could move forward, but limiting that work to unoccupied periods alone would have created significant schedule constraints. 

SOLUTION: Utility Reroutes to Roof Reinforcement Planned Around Campus Life

Close communication with the principal and administrative staff was essential at each step, allowing the project team to align field activities with student testing, on-campus events, staff access and other campus needs. Students and staff safety remained a primary priority throughout, with logistics continually adapted as work progressed from one area of the campus to another.

To manage this coordination, the team used Planera, a visual construction planner, to integrate project milestones with detailed field schedules. This gave the team a clear framework for coordinating construction around the school’s daily operations. Rather than a conventional schedule built solely around construction efficiency, activities were sequenced around instructional calendars, testing periods, school breaks, campus circulation and the availability of occupied spaces — giving the campus advance notice of daily construction activity and a direct channel to flag any access or operational concerns to the team.

Major utility reroutes, electrical transitions, structural reinforcement and other disruptive activities were concentrated during summer, holidays and scheduled school breaks whenever possible. This approach kept the project on schedule while minimizing disruption to students and staff in occupied areas.

To connect the old and new roof, the project team separated operation into strategic phases, installing new steel supports adjacent to existing joists during school breaks.

RESULT: A Fully Connected Campus with Zero Disruptions, Built with Expansion in Mind

The result was a collaborative construction process that allowed the district to keep serving its students without interruption, even as the existing facility was transformed into a more specialized middle school with opportunity for expansion.

The electrical relocation was completed without a single loss of power to the occupied building, leaving the campus with consolidated infrastructure built for both current and future needs, and the roof tie-in moved forward without disrupting occupied spaces.

What started out as an established, well-loved intermediate school was thoughtfully renewed for the next generation of Bastrop ISD middle school students.

Build Your Own Brochure

Download a customized brochure in just three steps.

Market Sectors

Services

Step 2

Complete this form to let us know where to send your brochure.

You're Done!

Click the button below to download your copy now or check your inbox to review the brochure at your leisure.